Subject: Approve & Authorize to fully close a portion of Stanford Avenue, on September 20, 2021, Kensington area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   09/07/2021
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Bob Hendry (925) 374-2136
cc: Larry Gossett- Engineering Services     Randolf Sanders- Engineering Services     Bob Hendry -Engineering Services     CHP     Sheriff - Patrol Division Commander    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     September  7, 2021
Monica Nino, County Administrator
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2021/264 approving and authorizing the Public Works Director, or designee, to fully close a portion of Stanford Avenue, on September 20, 2021 from 7:00 a.m. through 5:00 p.m., for the purpose of replacing a utility pole, Kensington area. (District I)

FISCAL IMPACT:

No fiscal impact.

BACKGROUND:

Existing utility pole has been identified for a scheduled replacement. Applicant previously was granted approval to close Stanford Avenue on August 11, 2021 per RC21-8 Resolution No. 2021/230. Applicant needs additional time to replace existing utility pole. Applicant shall follow guidelines set forth by the Public Works Department.

CONSEQUENCE OF NEGATIVE ACTION:

Applicant will be unable to close the road for planned activities.  