C. 2
To: Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: September  7, 2021
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Notice of Completion for the Bel Air Trail Crossing Project, Bay Point area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   09/07/2021
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Adelina Huerta, 925.313.2305
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     September  7, 2021
Monica Nino, County Administrator
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2021/258 accepting as complete the contracted work performed by GradeTech Inc., for the Bel Air Trail Crossing Project, as recommended by the Public Works Director, Bay Point area. Project No. 0662-6R4056 (District V)

FISCAL IMPACT:

The Project was funded by 18% Transportation Development Act Grant and 82% Local Road Funds.

BACKGROUND:

The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of June 24, 2021.

CONSEQUENCE OF NEGATIVE ACTION:

The contractor will not be paid and acceptance notification will not be recorded.