RECOMMENDATION(S):
APPROVE and AUTHORIZE the Chief Engineer, or designee, to execute Contract Amendment #4 with Horizon Water and Environment, LLC, effective August 24, 2020, to extend the Contract termination date from December 31, 2020 to March 31, 2021, and to increase the payment limit from $700,000 to $780,000 to complete necessary environmental compliance work for the Stream Maintenance Program, Countywide.
FISCAL IMPACT:
100% Flood Control District Funds.
BACKGROUND:
Due to revisions resulting from regulatory agency comments, this contract needs to be extended and the funding increased in order to complete environmental activities and obtain regulatory permits for the Stream Maintenance Program.
CONSEQUENCE OF NEGATIVE ACTION:
Without Board approval, environmental compliance may not be completed in a timely manner and necessary environmental clearances may not be obtained, which may jeopardize funding and delay maintenance work.
|