RECOMMENDATION(S):
APPROVE and AUTHORIZE the Conservation and Development Director, or designee, to execute a contract amendment with First Carbon Solutions, to increase the payment limit by $4,000 to new payment limit of $509,092 and extend the term from September 9, 2019 through September 9, 2020 to complete the Final Environmental Impact Report (FEIR) for the Tassajara Parks Project in the Tassajara Parks/San Ramon area.
FISCAL IMPACT:
None. The applicant is responsible for paying the costs of the additional work to complete the FEIR for the project.
BACKGROUND:
The Department of Conservation and Development (DCD) contracted with (FCS) in September of 2014 to prepare an Environmental Impact Report (EIR) for the Tassajara Parks Project involving the construction of a 125-unit residential subdivision with substantial dedication of park land in the Tassajara Valley/San Ramon area.
|