C. 10
To: Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: September  11, 2018
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Notice of Completion of Construction Contract for the San Pablo and Wildcat Creeks Levee Remediation Project, North Richmond area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   09/11/2018
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Kevin Emigh, 925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     September  11, 2018
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2018/469 accepting as complete the contracted work performed by Ghilotti Construction Company, for the San Pablo and Wildcat Creeks Levee Remediation Project, as recommended by the Chief Engineer, North Richmond area. (County Project No. 0662-6R4080) (District I)   
  

FISCAL IMPACT:

The project was funded by 63% Department of Water Resources Grant Funds and 37% Local Flood Control District Funds.  
  



BACKGROUND:

The Chief Engineer reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of May 16, 2018.  

CONSEQUENCE OF NEGATIVE ACTION:

The contractor will not be paid and acceptance notification will not be recorded.  