RECOMMENDATION(S):
APPROVE and AUTHORIZE the Interim Public Works Director, or designee, to apply and, if awarded, accept a grant for the 2017 Active Transportation Program (ATP) Augmentation to Cycle 3 to the California Transportation Commission (CTC) for the Appian Way Complete Streets Project and San Miguel Drive Complete Streets Project, as recommended by the Public Works Director. (District I & IV)
FISCAL IMPACT:
ATP will provide approximately $10,256,000 (84%) of funds for the Appian Way Complete Streets Project if awarded. The remaining project costs will be funded by $1,917,000 (15%) of local gas tax and $130,000 (1%) Richmond El Sobrante Area of Benefit (AOB) fees.
|