PDF Return
C. 3
To: Board of Supervisors
From: Julia R. Bueren, Public Works Director/Chief Engineer
Date: September  20, 2016
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Canal Road Bridge Replacement Project - CCWD Permit

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   09/20/2016
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Federal D. Glover, District V Supervisor
ABSENT:
Mary N. Piepho, District III Supervisor
Karen Mitchoff, District IV Supervisor
Contact: Angela Bell, (925)313-2337
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     September  20, 2016
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Public Works Director, or designee, to execute the Temporary Encroachment and Construction Permit, and any written amendments thereafter, for construction access and staging with Contra Costa Water District, effective September 20, 2016 through December 31, 2017, for the Canal Road Bridge Replacement Project. [Project Nos.: 0662-6R4080 and BRLO 5928 (108)]  

FISCAL IMPACT:

No Fiscal Impact.  

BACKGROUND:

Contra Costa County (County) is preparing for construction of the Canal Road Bridge Replacement Project (Project).  
  

BACKGROUND: (CONT'D)
The Bureau of Reclamation (USBR) owns the property adjacent to the canal which is leased by the Contra Costa Water District (District). USBR has delegated the authority to the District to issue the Permit for County’s temporary use of the canal property needed to construct the Project.  
  
The Permit will allow the County to access and occupy the Property during construction until the Project is completed, or December 31, 2017, whichever occurs first. As a condition of the Permit, the District has required the County to indemnify the District for claims arising out of the County’s use of the Property for the construction of the Project.

CONSEQUENCE OF NEGATIVE ACTION:

The Project could not be built without the temporary access to the canal property provided through the Temporary Encroachment and Construction Permit.   