RECOMMENDATION(S):
APPROVE and AUTHORIZE the Director of Airports, or designee, to execute a consulting services agreement with KSA Engineers Inc. to provide construction management services for the period July 1, 2021, to May 31, 2024, in connection with the terminal replacement project at Buchanan Field Airport, in an amount not to exceed $1,610,878.00. (District IV)
FISCAL IMPACT:
There is no negative impact on the General Fund. The total amount of the contract is $1,610,878.00, of which an estimated 72% (or $1,159,832.16) will be paid by the Federal Aviation Administration Airport Improvement Program and the remaining 28% (or $451,045.84) will be paid by the Airport Enterprise Fund.
BACKGROUND:
The Buchanan Field Airport Master Plan adopted by the Board on October 28, 2008, identifies a new general aviation terminal (Terminal Replacement Project) on the capital improvement list. Designs for the Terminal Replacement Project were completed by the KPA Group, pursuant to a contract dated March 12, 2019.
|