Subject: Approving the second extension of the Subdivision Agreement for subdivision SD14-09328, San Ramon (Dougherty Valley) area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   08/14/2018
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
ABSENT:
John Gioia, District I Supervisor
Contact: Randolf Sanders (925) 313-2111
cc: Jocelyn LaRocque- Engineering Services     Randolf Sanders- Engineering Services     Alex Lopez - Engineering Services     Trixie Gothro - Design & Construction     Ruben Hernandez - DCD     Shapell Homes, a Division of Shapell Industries, Inc.     The Continental Insurance Company     T -02/21/2019    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     August  14, 2018
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2018/455 approving the second extension of the Subdivision Agreement for subdivision SD14-09328, for a project being developed by Shapell Homes, Inc., a Division of Shapell Industries, a Delaware Corporation as recommended by the Public Works Director, San Ramon (Dougherty Valley) area. (District II)  
  

  

FISCAL IMPACT:

No fiscal impact





BACKGROUND:

The terminal date of the Subdivision Agreement needs to be extended. The developer has not completed the punch list items and has requested more time. (Approximately 100% of the work has been completed to date.) By granting an extension, the County will give the developer more time to complete improvements and keeps the bond current. The development is in the warranty period and the bond needs to be kept up to date.  
  

CONSEQUENCE OF NEGATIVE ACTION:

The terminal date of the Subdivision Agreement will not be extended and the developer will be in default of the agreement, requiring the County to take legal action against the developer and surety to complete the improvements.  
  