Subject: Trash and Abandoned Waste Cleanup and Removal Contract with Debri-Tech, Inc. Project #7517-WO7078

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   08/16/2016
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Mary N. Piepho, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Dan Jordan, (925) 313-2023
cc: Mike Carlson, Flood Control     Cece Sellgren, Flood Control     Michele Mancuso, Flood Control     Dan Jordan, Flood Control     Catherine Windham, Flood Control    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     August  16, 2016
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract amendment with Debri-Tech, Inc., to increase the payment limit from $500,000 to a new payment limit of $1,000,000, to provide as-needed assistance with trash and abandoned waste cleanup and removal for the Contra Costa County Watershed Program (CWP), with no change to the original term of August 1, 2015 through July 31, 2018, Countywide.  

FISCAL IMPACT:

100% Stormwater Utility Assessment Revenue Funds.

BACKGROUND:

The CWP requires as-needed assistance with trash and abandoned waste cleanup and related removal activities in order to remain in compliance with Contra Costa County’s stormwater NPDES (National Pollutant Discharge Elimination System) permit from the California Regional Water Quality Control Board(s).





CONSEQUENCE OF NEGATIVE ACTION:

Without the approval of this contract amendment by the Board of Supervisors, Contra Costa County will be out of compliance with its stormwater permits from the Regional Water Quality Control Board(s).