On March 12, 2013, the Board of Supervisors approved the CSA for construction management services with Consolidated CM with a payment limit of $1,246,000.
On December 3, 2013, the Board approved Amendment No. 1 to the CSA to increase the payment limit by $350,000 to a new payment limit of $1,596,000.
On February 11, 2014, the Board approved Amendment No. 2 to the CSA to increase the payment limit by $561,773 to a new payment limit of $2,157,773.
On May 13, 2014, the Board approved Amendment No. 3 to the CSA to increase the payment limit by $200,000 to a new payment limit of $2,357,773.
On October 7, 2014, the Board approved Amendment No. 4 to the CSA to increase the payment limit by $200,000 to a new payment limit of $2,557,773.
Proposed Amendment No. 5 will amend the term by changing the termination date from June 1, 2015 to June 20, 2017 and will increase the payment limit by $50,000 to a new Payment Limit of $ 2,607,773 in order to provide additional construction management services.
The consultant would not be compensated for services needed to complete the project.