RECOMMENDATION(S):
APPROVE the Bay Point Curb Ramp Project contingency fund increase of $45,000 for a new contingency fund total of $62,766.00, and a new payment limit of $240,426.00, effective August 9, 2016, and
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute Contract Change Order No. 1 with Rosas Brothers Construction, effective August 9, 2016, in an amount not to exceed $58,478.00. Project No. 0662-6U4031-16
FISCAL IMPACT:
Project is being funded by 100% Local Road Funds.
|