100% General Fund - Facilities Life-cycle Investment Program funds.
The purpose of this project is to maintain, repair, and restore portions of an existing public historical structure in a manner consistent with the Secretary of the Interior's Standards for the Treatment of Historic Properties with Guidelines for Preserving, Rehabilitating, Restoring, and Reconstructing Historic Buildings.
The Contra Costa County Finance Building at 625 Court Street, Martinez, was identified under the Facilities Life-cycle Improvement Program (FLIP) as a building that requires immediate attention. The project will install a new roof and ornamental sheet metal, seismically upgrade portions of the existing structural system, create new Americans with Disability Act (ADA) compliant restrooms, replace public counter areas, install a new fire sprinkler system, clean and repaint the masonry exterior, replace the main electrical switchgear, and refurbish doors and guard rails.
Plans and specifications for the project have been prepared for the Public Works Department by Carey & Co. Inc. and filed with the Clerk of the Board by the Public Works Director. Bids were received and opened by the Public Works Department on July 23, 2015, and bids were as follows:
BIDDER |
TOTAL BASE BID |
ADD. ALTERNATE 1 |
ADD. ALTERNATE 2 |
Thompson Builders Corp., Novato |
$4,609,175 |
$150,000 |
$200,000 |
Alten Construction, Richmond |
$5,014,475 |
$216,000 |
$135,000 |
Vila Construction Co., Richmond |
$6,547,404 |
$404,007 |
$353,022 |
All the base bids received were below the Architect's Estimate of $7,000,000. Staff has evaluated the low bid submitted by Thompson Builders and their good faith effort documentation. Staff has determined that Thompson Builders bid is responsive and their good faith effort documentation is in compliance with the County's Outreach Program. The Public Works Director recommends the Board award the construction contract, including the Base Bid work plus Additive Alternates #1 and #2, to Thompson Builders, the lowest responsive and responsible bidder, in the amount of $4,959,175.
Pursuant to the County's Project Labor Agreement ("PLA") policy, a PLA is required for this project. Thompson Builders has signed a PLA and, as condition of contract award, Thompson Builders subcontractors will also be required to sign the PLA.
The general prevailing rates of wages, which shall be the minimum rates paid on this project, are on file with the Clerk of the Board, and copies are available to any party upon request.
If the construction contract is not awarded, the project will not move forward and the building will continue to deteriorate and leak.