PDF Return
C. 16
To: Contra Costa County Flood Control District Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: July  26, 2022
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: On-Call Contract Amendment 2 with Balance Hydrologics, Inc., Countywide.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   07/26/2022
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Tim Jensen, (925) 313-2390
cc: Allison Knapp, Deputy Chief Engineer     Tim Jensen, Flood Control     Michael Taylor, Flood Control     Catherine Windham, Flood Control    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     July  26, 2022
Monica Nino, County Administrator
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Chief Engineer, Contra Costa County Flood Control and Water Conservation District (FC District), or designee, to execute a Consulting Services Agreement (Contract) Amendment with Balance Hydrologics, Inc., effective July 1, 2022, to increase the payment limit by $170,000 to a new payment limit of $370,000 for on-call professional engineering services relating to hydrology/hydraulic studies and modeling, with no change to the term of May 14, 2019 through May 14, 2023, Countywide.

FISCAL IMPACT:

This project, including the Contract Amendment, will be funded by 100% FC District Funds (Project No.: Various).

BACKGROUND:

The FC District provides regional flood protection, technical information, hydrology data and education to cities and residents, and environmental stewardship for over 70 miles of streams and several detention basins as part of the County’s flood protection system. The FC District is increasing the payment limit of its on-call support for hydrology/hydraulic studies for continued services.



CONSEQUENCE OF NEGATIVE ACTION:

Without the approval of the Board of Supervisors, the FC District will not be able to obtain on-call services for professional engineering and technical services relating to hydrology/hydraulic studies and modeling.

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved