RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract amendment with Vanir Construction Management, Inc. (Vanir), effective July 30, 2019, to increase the payment limit by $400,000 to a new payment limit of $10,404,948, and to extend the term from May 9, 2022 to May 9, 2023, for construction management services for the renovation of Module M at the Martinez Detention Facility, 1000 Ward Street, Martinez area.
FISCAL IMPACT:
The contract amount amendment, not to exceed $400,000, is part of the approved general purpose revenue/reserves budget (100% General Fund).
BACKGROUND:
On May 9, 2017, the County awarded a contract to Vanir Construction Management, Inc., for construction management services for two sites at a total allotted amount of $6,000,000, with a completion date of 3 years from the effective date of May 9, 2017.
|