RECOMMENDATION(S):
ADOPT Resolution No. 2019/85 approving and authorizing the Public Works Director, or designee, to fully close a portion of Coventry Road between a point 200’ south of Valley Road and the north end of Coventry Road, for 45 consecutive working days between August 26, 2019 and October 10, 2019 from 7:00 AM through 5:00 PM, for the purpose of installing a 42" welded steel pipe water main and butterfly valves by the East Bay Municipal Utility District, Kensington area. (District I)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
East Bay Municipal Utility District (EBMUD) is planning to replace the 5.4 million gallon San Pablo Clearwell (water storage tank) and rehabilitate portions of the San Pablo Water Treatment Plant, both of which are located within EBMUD's San Pablo Water Treatment Plant site in Kensington.
|