PDF Return
C. 7
To: Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: July  10, 2018
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Accept completion of warranty period and release of cash deposit for performance Subdivision Agreement (ROWL), SD08-09165, San Ramon (Dougherty) area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   07/10/2018
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Jocelyn LaRocque - (925)313-2315
cc: Jocelyn LaRocque- Engineering Services     Trixie Gothro - Design & Construction     Chris Hallford -Mapping     Alex Lopez - Engineering Services     Ruben Hernandez - DCD     Chris Low - City of San Ramon     Shapell Homes, a Division of Shapell Industries, Inc.     The Continental Insurance Company    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     July  10, 2018
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2018/239 accepting completion of the warranty period for the Subdivision Agreement (Right-of-Way Landscaping) and release of cash deposit for faithful performance, for subdivision SD08-09165, for a project developed by Shapell Homes, A Division of Shapell Industries, Inc., A Delaware Corporation, as recommended by the Public Works Director, San Ramon (Dougherty Valley) area. (District II)  
  

FISCAL IMPACT:

100% Developer Fees. The funds to be released are developer fees that have been held on deposit.  
  




FISCAL IMPACT: (CONT'D)
  

BACKGROUND:

The landscape improvements have met the guarantee performance standards for the warranty period following completion and acceptance of the improvements.  
  

CONSEQUENCE OF NEGATIVE ACTION:

The developer will not receive a refund of the cash deposit, the Subdivision Agreement (Right-of-Way Landscaping) and performance/maintenance surety bond will not be exonerated, and the billing account will not be liquidated and closed.  
  