C. 65
To: Board of Supervisors
From: Julia R. Bueren, Public Works Director/Chief Engineer
Date: July  19, 2016
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Accepting and Giving Notice of Completion and Demolition Contract, 305 Chesley Avenue, Richmond

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   07/19/2016
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Mary N. Piepho, District III Supervisor
Federal D. Glover, District V Supervisor
ABSENT:
Karen Mitchoff, District IV Supervisor
Contact: Jewel Lopez, (925) 313-2191
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     July  19, 2016
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2016/455 accepting as complete the contracted work performed by W.C. Maloney, Inc., for demolition of Assessor’s Parcel No. 409-080-013, also identified as 305 Chesley Avenue in Richmond, for the Heritage Point Redevelopment Project, as recommended by the Public Works Director. (Project No.:0676-6P4082)  
  

FISCAL IMPACT:

100% Successor Agency Funds.

BACKGROUND:

The Public Works Director reports that said work has been inspected and complies with the special provisions and standard specifications and recommends its acceptance as completed as of March 21, 2016, for Assessor’s Parcel No. 409-080-013, also identified as 305 Chesley Avenue in Richmond.


CONSEQUENCE OF NEGATIVE ACTION:

W.C. Maloney, Inc., will not be paid and acceptance notification will not be recorded.  