Subject: Amendment #26-692-8 with Applied Remedial Services, Inc.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   07/21/2015
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Mary N. Piepho, District III Supervisor
Karen Mitchoff, District IV Supervisor
ABSENT:
Federal D. Glover, District V Supervisor
Contact: Anna Roth, 370-5101
cc: T Scott     N Rios    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     July  21, 2015
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

Approve and authorize the Health Services Director, or his designee, to execute, on behalf of the County, Contract Amendment Agreement #26-692-8 with Applied Remedial Services, Inc., a corporation, effective June 1, 2015, to increase the payment limit by $3,500, from $290,000 to a new payment limit of $293,500, with no change in the original term of January 1, 2015 through December 31, 2015.

FISCAL IMPACT:

This amendment is funded 100% in the Hospital Enterprise I Fund. (No rate increase)

BACKGROUND:

On January 6, 2015, the Board of Supervisors approved Contract #26-692-6 with Applied Remedial Services, Inc., for the period from January 1, 2015 through December 31, 2015, for the provision of removal and disposal of hazardous waste and chemicals for the Contra Costa Regional Medical Center and Contra Costa Health Centers.  
  

BACKGROUND: (CONT'D)
Approval of Contract Amendment Agreement #26-692-8 will allow the Contractor to provide additional removal and disposal of hazardous waste including an additional pick up at the Detention Facility in Martinez, through December 31, 2015.  

CONSEQUENCE OF NEGATIVE ACTION:

If this amendment is not approved, the Contractor will not be able to provide hazardous waste removal and disposal for the Detention Facility in Martinez.