C. 46
To: Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: June  5, 2018
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: APPROVE a contract with Garland/DBS Inc.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   06/05/2018
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Stan Burton 925-313-7077
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     June  5, 2018
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract with Garland/DBS Inc., in an amount not to exceed $20,000,000, to provide on-call roofing repair and exterior waterproofing services, for the period June 1, 2018 through May 31, 2021, Countywide.

FISCAL IMPACT:

This cost is to be funded through Facilities Services maintenance budget and user departments. (100% General Fund)  











BACKGROUND:

Public Works Facilities Maintenance is responsible for roofing repairs and maintenance. Capital Projects and Facilities have been budgeted with several FLIP (Facility Life-Cycle Investment Program) projects. Since 2015, $15 million has been spent on roofing and exterior waterproofing projects at about 1/3 of the County-owned buildings. For Fiscal Year 2018/19, about $8 million of roofing and exterior waterproofing projects have already been planned and routine inspections of County buildings have identified many more that will need repair within the next three years of this contract term. Government Code Section 25358 authorizes the County to contract for maintenance and upkeep of County facilities. Roof repair and exterior waterproofing is an important part of keeping County buildings safe and operational. Public Works is requesting this contract be approved for a period covering the next three years.

CONSEQUENCE OF NEGATIVE ACTION:

If this contract is not approved, roofing repair and exterior waterproofing services with Garland/DBS Inc. will not proceed and buildings with exterior water leaks will cost more to repair due to cascading costs of mold remediation, interior water damage repairs, and disruption of work areas.  