Subject: Approve the CFD North Richmond Median Electrification Project and related actions under CEQA

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   06/07/2016
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Mary N. Piepho, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Alex Nattkemper, (925) 313-2364
cc: Liza Mangabay     Leigh Chavez     Susan Cohen     Michael McAfee    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     June  7, 2016
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE the Community Facilities District (CFD) North Richmond Median Electrification Project (Project) and AUTHORIZE the Public Works Director, or designee, to advertise the Project, North Richmond area. [County Project No. 7485-6X5082, DCD-CP# 16-12] (District I).  
  

DETERMINE the Project is a California Environmental Quality Act (CEQA), Class 1(b) Categorical Exemption, pursuant to Article 19, Section 15301(b) of the CEQA Guidelines, and  

  

RECOMMENDATION(S): (CONT'D)
DIRECT the Director of Conservation and Development to file a Notice of Exemption with the County Clerk, and  
  
AUTHORIZE the Public Works Director to arrange for payment of a $25 fee to Conservation and Development for processing, and a $50 fee to the County Clerk for filing the Notice of Exemption.

FISCAL IMPACT:

100% CFD 2006-1 Funds.  

BACKGROUND:

The purpose of this Project is to install eight (8) electrical outlets with lockable, weatherproof covers on the Fred Jackson Way median island in North Richmond. The community envisions the median island as a location for periodic community events. The installation of electrical outlets along the median will help to better serve this purpose. Encroachment permits would be required for any events scheduled at this location and would include providing approved access to the electrical outlets.  

CONSEQUENCE OF NEGATIVE ACTION:

Delay in approving the project may result in a delay of design, construction, and may jeopardize funding.  