To: Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: May  9, 2023
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Amendments to Cooperative Agreement & Freeway Maintenance Agreement: Bailey Road & SR4 Interchange Pedestrian & Bike Improvement Proj., Bay Point area

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   05/09/2023
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Ken Carlson, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Nancy Wein, 925.313.2275
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     May  9, 2023
Monica Nino, County Administrator
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE an Amendment to the Cooperative Agreement between the County and the State of California, Department of Transportation (Caltrans), related to receiving federal funding for the construction of the Bailey Road and State Route 4 Interchange Pedestrian and Bicycle Improvement Project (Project), Bay Point; and an amendment to the Freeway Maintenance Agreement with Caltrans for the same project; and AUTHORIZE the Public Works Director to execute both amendments on behalf of the County. (District V) (Project 0662-6R4121)

FISCAL IMPACT:

Under the Amended Cooperative Agreement, the Road Fund will receive up to $3.38 million in Active Transportation Program (ATP) funding for the construction of the project. The amendment to the existing Freeway Maintenance Agreement only updates maintenance responsibilities of both parties in the interchange area. (100% Local Road Fund)

BACKGROUND:

In August of 2021, the County executed a Cooperative Agreement with Caltrans to receive federal funds for the Project. An ATP grant was awarded to the County for the preliminary engineering and construction phases of the project.  



BACKGROUND: (CONT'D)
      
    The project was completed in 2021 and consisted of the following elements:
    1. Remove the north-side loop off-ramp and pedestrian tunnel.
    2. Improve the westbound off-ramp on the east side of Bailey Road to accommodate north and southbound traffic turning onto Bailey Road.
    3. Change the south-side eastbound loop off-ramp to a fully signalized T-intersection at Bailey Road.
    4. Eliminate acceleration lanes on Bailey Road to accommodate bicycle lanes and widened sidewalks.
    5. Enhance existing pedestrian crossings at the BART Access Road and Canal Road intersections on Bailey Road.
    It is proposed to amend the existing agreement to redistribute funds between the construction engineering and contract allocations to maximize available funding. The total grant remains the same.  
      
    It is also proposed to amend the existing Freeway Maintenance Agreement with Caltrans to update the areas of maintenance responsibilities to be consistent with the newly constructed improvements.

    CONSEQUENCE OF NEGATIVE ACTION:

    Failure to approve the amendment to the Cooperative Agreement would jeopardize the County’s ability to receive the total amount of ATP funds for the project. If the amendment to the Freeway Maintenance Agreement is not approved, the County will be unable to submit the final project invoice to Caltrans.