Subject: Accepting and Declaring certain roads as county roads, Bethel island Bridge Replacement Project No. 0662-6R4043-02, Bethel Island area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   05/10/2022
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Jim Stein (925) 313-2343
cc: Jocelyn LaRocque- Engineering Services     Jim Stein - Survey's     Chris Lau - Maintenance     Chris Hallford -Mapping     Jerry Fahy- Transportation     Monish Sen - Transportation     Dante Morabe - Design & Construction     Jessica Dillingham- Real Property     Renee Hutchins - Records     Karen Piona- Records     CHP     Sheriff - Patrol Division Commander    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     May  10, 2022
Monica Nino, County Administrator
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT RESOLUTION No. 2022/151 accepting and declaring certain roads as county roads (Wells Road and South Levee Access Road), Bethel Island Bridge Replacement Project No. 0662-6R4043-02, as recommended by the Public Works Director, Bethel Island area. (District III)  

FISCAL IMPACT:

No fiscal impact.

BACKGROUND:

Wells Road and South Levee Access Road were constructed as part of the Bethel Island Bridge Replacement Project No. 0662-6R4043-02. The height of the new bridge and the grade change of the roadway approach to it necessitated the construction of these two roads to maintain access to the local businesses and private roadways. Property rights were acquired in 2009 and 2010 as part of the bridge project and the Board of Supervisors accepted the improvements as complete in 2011. It was recently discovered that these roads were not formally accepted into the County Maintained Roads log.



CONSEQUENCE OF NEGATIVE ACTION:

The roads will not be part of the County Maintained Roads system and the County will not be eligible for State gas tax funds.