PDF Return
C. 19
To: Board of Supervisors
From: Keith Freitas, Airports Director
Date: May  7, 2019
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: APPROVE AND AUTHORIZE AMENDMENT 2 TO CONSULTING SERVICES AGREEMENT WITH C & S ENGINEERS, INC.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   05/07/2019
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Beth Lee (925) 681-4200
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     May  7, 2019
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Director of Airports, or designee, to execute Amendment 2 to the Consulting Services Agreement with C & S Engineers, Inc. to add four additional Subconsultants.  

FISCAL IMPACT:

There is no negative impact on the General Fund. There is no change to the contract amount with all contract costs being paid by the Airport Enterprise Fund.  

BACKGROUND:

C & S Engineers, Inc. (Contractor) would like to have Shah Kawasaki Architects (SKA), Chang Consultants, R.E.Y. Engineers, Inc. and HELIX Environmental Planning added to their Consulting Services Agreement as their subconsultants. The Contractor will need the additional subconsultants to complete the following Airport required tasks:  



BACKGROUND: (CONT'D)
    1. Buchanan Field Drainage & Flood Control Study Update
    2. Review and sign-off of the Site Plan by an Architect so that the permits can be issued, and the Byron ARFF garage can be installed.

    CONSEQUENCE OF NEGATIVE ACTION:

    If not approved, Contractor will not be able to use Shah Kawasaki Architects (SKA), Chang Consultants, R.E.Y. Engineers, Inc. and HELIX Environmental Planning to perform the additional work required to complete the Drainage and Flood Control Study Update and the permits for the Byron ARFF Garage will not be issued further stalling the installation of the metal structure.

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved