RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute Contract Amendment No. 1 to the Consulting Services Agreement (CSA) with WSP USA, Inc. effective May 1, 2018, to increase the payment limit by $75,000 to a new payment limit of $375,000, for construction management services for the Byron Highway and Camino Diablo Intersection Improvements Project (Project), for the period of May 9, 2017, through June 30, 2018, Byron area. (County Project No. 0662-6R4094/Federal Project No. HSIPL-5928(117)) (District III)
FISCAL IMPACT:
This project, including the CSA, is funded by 23% Highway Safety Improvement Program Grant Funds, 17% Measure J Return to Source Funds, 12% East County Regional Area of Benefit Funds, and 48% Local Road Funds.
CONSEQUENCE OF NEGATIVE ACTION:
The project completion would be delayed and federal funds would be in jeopardy.
|