RECOMMENDATION(S):
AUTHORIZE the Public Works Director, or designee, to execute a Pacific Gas & Electric work agreement for the Hazel Avenue Storm Drain Repair, East Richmond Heights area.
FISCAL IMPACT:
100% Local Road Funds.
BACKGROUND:
This work is located on Hazel Avenue, between Ralston Avenue and Sonoma Street in the East Richmond Heights area. The Hazel Avenue Storm Drain Repair work will require the installation of a manhole, two curb inlets, 42" storm drain pipe, curb ramp, and repair affected sidewalk and pavement. A portion of this work will be near a utility pole requiring the need for pole support to complete the storm drain repair work. This Pacific Gas & Electric work agreement details the arrangement between the County and Pacific Gas & Electric to have Pacific Gas & Electric crews perform the pole support and the cost for this work.
CONSEQUENCE OF NEGATIVE ACTION:
The utility pole support will not be performed which will delay the storm drain repair project.
|