The construction contract will be funded by 100% Discovery Bay West Mitigation Fees.
The above project was previously approved by the Board of Supervisors, plans and specifications were filed with the Board, payment to the Habitat Conservancy Plan for $113,860 has been made, and bids were invited by the Public Works Director. On March 21, 2017, the Public Works Department received bids from the following contractors:
BIDDER, TOTAL AMOUNT, BOND AMOUNTS
Granite Rock Company: $4,254,322.00; Payment: $4,254,322.00; Performance: $4,254,322.00
O.C. Jones & Sons, Inc.: $4,447,384.5
Bay Cities Paving & Grading, Inc.: $4,611,364.76
Goodfellow Top Grade Construction, Inc.: $4,766,624.40
Granite Construction Company: $4,987,558.50
A. Teichert & Son, Inc.: $5,191,887.00
The bidder listed first above, Granite, submitted the lowest responsive and responsible bid, which is $193,062.50 less than the next lowest bid.
The Public Works Director has reported that Granite documented an adequate good faith effort to comply with the requirements of the County’s Outreach Program, as provided in the project specifications, and the Public Works Director recommends that the construction contract be awarded to Granite.
The Public Works Director recommends that the bid submitted by Granite is the lowest responsive and responsible bid, and this Board concurs and so finds.
The Board of Supervisors previously adopted the Mitigated Negative Declaration on December 15, 2015, in compliance with the California Environmental Quality Act, and a Notice of Determination was filed with the County Clerk on December 17, 2015.
The general prevailing rates of wages, which shall be the minimum rates paid on this project, have been filed with the Clerk of the Board, and copies will be made available to any party upon request.
Construction of the project would be delayed, and the project might not be built.