RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute Contract Amendment No. 1 with Mark Thomas & Company, Inc., effective May 2, 2017, to increase the payment limit by $258,000 to a new payment limit of $1,350,000 to provide additional professional engineering services, including construction support, and extend the termination date by one year to a new termination date of December 31, 2019, for the Kirker Pass Road Northbound Truck Climbing Lane Project, Concord area. (Project No. 0662-6R4052)
FISCAL IMPACT:
The Consulting Services Agreement will be funded by the Measure J Transportation Sales Tax (Measure J) Program. The construction of the project will be funded by federal funds from the State Transportation Improvement Program (STIP), as well as funding from Measure J and other local road funds.
|