Subject: Notice of Completion of construction contract for the Byron Airport Pavement Enhancements Project, Byron area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   04/19/2016
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Mary N. Piepho, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Kevin Emigh, 925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     April  19, 2016
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2016/319 accepting as complete the contracted work performed by Maxwell Asphalt, Inc. for the Byron Airport Pavement Enhancements Project, as recommended by the Public Works Director, Byron area. County Project No. 4875-4650-SAS-6X5314 / Federal Project No. AIP 03-06-0008-014  

FISCAL IMPACT:

Project was funded by 90% Federal Aviation Administration (FAA) Airport Improvement Program (AIP) Funds, 2.25% Caltrans Funds, 7.75% Airport Enterprise Funds.  

BACKGROUND:

The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of March 24, 2016.  



CONSEQUENCE OF NEGATIVE ACTION:

The contractor will not be paid and acceptance notification will not be recorded.  