PDF Return
C. 8
To: Board of Supervisors
From: Julia R. Bueren, Public Works Director/Chief Engineer
Date: April  14, 2015
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Consulting Services Agreement with 4LEAF, Inc., Countywide. Project No. Various

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   04/14/2015
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Mary N. Piepho, District III Supervisor
Karen Mitchoff, District IV Supervisor
ABSENT:
Federal D. Glover, District V Supervisor
Contact: Kevin Emigh (925) 313-2000
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     April  14, 2015
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract with 4LEAF, Inc., in an amount not to exceed $300,000 for on-call construction management services for the period April 14, 2015 through April 14, 2018, Countywide.

FISCAL IMPACT:

Work performed under this on-call consulting services agreement is funded by developer fees, local, state and federal funds for road, flood control, and airport projects.

BACKGROUND:

The Public Works Department is involved in various projects in the County which require construction management services for road, flood control, and airport projects. After a solicitation process, this firm was selected as one of the six firms to provide construction management services on an “on-call” basis. The consultant will augment Public Works Design/Construction staff on an as-needed basis. They will be used as an extension of Public Works staff during busy times when extra help is needed or when in-house expertise is not available. This on-call consulting services agreement will be in effect for three years.




CONSEQUENCE OF NEGATIVE ACTION:

Without approval from the Board of Supervisors, there will be possible delay in completing projects requiring construction management services. Executing this contract will facilitate the process of construction for various Public Works projects requiring a construction management expertise.

CHILDREN'S IMPACT STATEMENT:

Not applicable.

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved