PDF Return
C. 58
To: Board of Supervisors
From: William Walker, M.D., Health Services Director
Date: April  14, 2015
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Amendment/Extension #23-478-8 with Santa Rosa Consulting, Inc.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   04/14/2015
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Mary N. Piepho, District III Supervisor
Karen Mitchoff, District IV Supervisor
ABSENT:
Federal D. Glover, District V Supervisor
Contact: David Runt, 925-313-6228
cc: K Cyr     C Rucker    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     April  14, 2015
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

Approve and authorize the Health Services Director, or his designee, to execute, on behalf of the County, Contract Amendment/Extension Agreement #23-478-8 with Santa Rosa Consulting, Inc., a corporation, effective September 1, 2014, to amend Contract #23-478-7 to modify the payment provisions with no change in the original payment limit of $1,500,000 and to extend the term from June 30, 2015 to through June 30, 2016.

FISCAL IMPACT:

This amendment is funded 100% by Enterprise Fund I. (Adding provision of $40,000 for travel reimbursement)

BACKGROUND:

On January 6, 2015, the Board of Supervisors approved Contract #23-478-7, with Santa Rosa Consulting, Inc., for the period from September 1, 2014 through June 30, 2015, for the provision of consulting, technical support, training and project management to the Department’s Information Systems Unit for County’s computer systems. Due to a mutual mistake, the Division and Contractor did not include provisions for travel reimbursement needed on behalf of the County through the term of this Contract. Approval of Contract Amendment Agreement #23-478-8 will add provisions for travel expenses with no increase in the total payment limit and allow the Contractor to continue to provide services through June 30, 2016.

CONSEQUENCE OF NEGATIVE ACTION:

If this amendment/extension is not approved, Contractor will not be paid for travel expenses incurred during the term of the contract.

CHILDREN'S IMPACT STATEMENT:

Not applicable.