From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: March  2, 2021
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: APPROVE and AUTHORIZE the Right of Way Contract and Accept Grant Deed for the Byron Highway/Byer Road Safety Improvements Project, District III

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   03/02/2021
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Jann Edmunds, 925. 957-2454
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     March  2, 2021
Monica Nino, County Administrator
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Public Works Director, or designee, to execute the Right of Way Contract (Contract), and ACCEPT the Grant Deed (Deed) on a portion of property located adjacent to Byron Highway identified as Assessor’s Parcel Number 003-100-012 from Timothy S. Broderick, et. al., to Contra Costa County (County) in connection with the Byron Highway/Byer Road Safety Improvements Project (Project), pursuant to Government Code Section 25350.60 (Project No.: 0662-6R4147, Federal Project No.: HSIPL-5928 (143) (DCD - CP # 18-04)  
  

AUTHORIZE the Public Works Director, or designee, to execute said Right of Way Contract on behalf of the County.  





RECOMMENDATION(S): (CONT'D)
  
APPROVE payment in the amount of $20,735, for said property rights; and AUTHORIZE the Auditor-Controller to issue a check in said amount payable to Chicago Title Company, 1200 Concord Avenue, Suite 400, Concord, CA 94520, their Escrow No. 36301736-363-LB-KD to be forwarded to the Real Estate Division for delivery.  
  
DIRECT the Real Estate Division to have the above referenced Deed delivered to the Title Company for recording in the Office of the County Recorder.  

FISCAL IMPACT:

26% Highway Safety Improvement Funds, 3% Local Road Funds, 18% East County Area of Benefit Funds, 7% Discovery Bay Area of Benefit Funds, 46% Discovery Bay West Funds.

BACKGROUND:

The County intends to construct the Project and widen Byron Highway in order to install traffic safety improvements along Byron Highway between Byer Road intersection to Hoffman Lane.  
  
As a condition of the contract, Grantors have requested indemnification from the County.  
  
On December 4, 2018, the Board of Supervisors approved the project and determined the project was exempt from CEQA (CP #18-04).

CONSEQUENCE OF NEGATIVE ACTION:

The Project will not have sufficient land rights to allow construction in accordance with the approved plans and specifications.  