To: Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: March  26, 2019
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Advertise the 2019 On-Call Trucking Services Contracts for Aggregate Stockpiling and Transportation

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   03/26/2019
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
ABSENT:
Diane Burgis, District III Supervisor
Contact: Caroline Tom (925) 313-7007
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     March  26, 2019
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

AUTHORIZE the Public Works Director, or designee, to advertise for 2019 On-Call Trucking Services Contracts for Aggregate Stockpiling and Transportation, Contract No. 0672-6U2181, for the stockpiling and transportation of chip seal aggregate that will be used for the Public Works Department’s chip seal program, Countywide.  
  

FISCAL IMPACT:

100% Local Road Funds  
  




BACKGROUND:

The Public Works Department will use the 2019 On-Call Trucking Services Contracts for Aggregate Stockpiling and Transportation to provide trucking services for the transportation of chip seal aggregate from the quarry to various stockpile locations throughout Contra Costa County, and also for the transportation of the chip seal aggregate from the stockpile locations to various roads within Contra Costa County. The aggregate will be used by Public Works Maintenance crews for routine pavement surface treatment activities on various roads within Contra Costa County.   
  
The Public Works Department intends to award one contract up to $900,000 with a term of one year, with the option of two (2) one-year extensions. The contract will be used as needed with no minimum amount that has to be spent.  

CONSEQUENCE OF NEGATIVE ACTION:

The Public Works Department may be unable to complete the chip seal program.  
  