Subject: APPROVE the ADA Upgrades to Juvenile Hall Main Building Project and take related actions under CEQA.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   03/12/2019
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
ABSENT:
Diane Burgis, District III Supervisor
Contact: Sandeep Singh, (925) 313-2022
cc: Ave Brown - Environmental Division Manager    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     March  12, 2019
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE the ADA Upgrades to Juvenile Hall Main Building Project (Project), Martinez area. [County Project No.250-1728, DCD-CP#19-02] (District V)  
  

DETERMINE the Project is a California Environmental Quality Act (CEQA), Class 1(a) Categorical Exemption, pursuant to Article 19, Section 15301 of the CEQA Guidelines, and  

  




RECOMMENDATION(S): (CONT'D)
DIRECT the Director of Department of Conservation and Development to file a Notice of Exemption with the County Clerk, and  
  
AUTHORIZE the Public Works Director, or designee, to arrange for payment of a $25 fee to the Department of Conservation and Development for processing, and a $50 fee to the County Clerk for filing the Notice of Exemption.  
  

FISCAL IMPACT:

Estimated Project cost: $572,000. 100% Facilities Lifestyle Improvement Program Funds.  
  

BACKGROUND:

The purpose of this Project is to improve accessibility for public and institutional portions of the juvenile detention facility main building.  
  
The Project consists of revisions and improvements of roughly 740 square feet of space in multiple locations including the remodel of several restrooms, drinking fountains, kitchen spaces, and services areas to meet ADA requirements.  
  
On November 13, 2018, the Board of Supervisors awarded a job order contract (JOC) for repair, remodeling, and other repetitive work to be performed pursuant to the Construction Task Catalog to each of Mark Scott Construction, Inc., Aztec Consultants, and Staples Construction Company, Inc., each in the amount of $2,500,000. This project is expected to be performed by one of the three JOC contractors. A task order catalogue has been prepared for the JOC contractor to complete this Project. In the event that the Project is not performed by the JOC contractor, the Public Works Department will return to the Board for approval of plans and specifications and authorization to advertise and solicit bids.  
  

CONSEQUENCE OF NEGATIVE ACTION:

Delay in approving the project may result in a delay of design, construction, and may jeopardize funding.  