RECOMMENDATION(S):
ADOPT Resolution No. 2019/67 accepting as complete the contracted work performed by Bridgeway Civil Constructors, Inc., for the Marsh Creek Road Bridge Replacement Project, as recommended by the Public Works Director, Clayton area. (Federal Project No. BRLS 5928 (107), County Project No. 0662-6R4079) (District III)
FISCAL IMPACT:
Project was funded by 87% Federal Highway Bridge Program Funds, 11% Local Road Funds and 2% Contra Costa Water District Funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of February 19, 2019.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
|