BACKGROUND:
On September 22, 2015, the Board approved modifications to the Keller Canyon Landfill Land Use Permit 2020-89 (“Permit”). Among the changes was the addition of conditions restricting disposal of direct haul C&D material (“Conditions”) at the landfill. The Board determined that this particular change would take effect on March 22, 2017. In response to the Board’s action, the landfill operator, Keller Canyon Landfill Company, Inc. (“Keller”), filed a lawsuit against the County.
Keller has requested an extension of the March 22, 2017 deadline to stop admitting direct haul construction and demolition material trucks at the landfill. A change in the date by which the operator must comply with the Conditions from March 22, 2017, to August 31, 3017, would preserve the status quo between Keller and the County during the initial stage of the litigation. The date change would not amend the terms of the Permit.
CONSEQUENCE OF NEGATIVE ACTION:
The March 22, 2017 compliance deadline would not be changed.
CLERK'S ADDENDUM
Speakers: Laura Wright, City Manager of Pittsburg (handout-photo); Garrett Evans, Assistant City Manager of Pittsburg (handout-letter); Gregory Scorio, resident of Pittsburg; Lisa Della Rocca, resident of Pittsburg; Alberto Ruiz, President, Teamsters Local 315; Marc Lopez, Local 342; Monica White, resident of Orinda; Evan Edgar, Recyclers; Ken Edgecomb, resident of Concord, Mike Dicaprio; Dana Dean, Counsel for Monica White and Evan Edgar,
DECLINED to extend the date by which the operator of Keller Canyon Landfill must comply with the conditions of the land use permit for the facility that restrict the acceptance and disposal of direct haul of construction and demolition (C&D) material at the landfill from March 22, 2017 to August 31, 2017.