RECOMMENDATION(S):
ADOPT Resolution No. 2023/23 approving and authorizing the Public Works Director, or designee, to fully close a portion of Lillian Street between 2nd Avenue and 7th Avenue, and all of 7th Avenue and Del Mar Circle, between February 8, 2023 and April 28, 2023 from 7:00 a.m. through 5:00 p.m., for the purpose of an infrastructure renewal project including the replacement of 1,375' of 6” water main, service transfers, hydrants and connections, Crockett area. (District V)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
Applicant, East Bay Municipal Utility District, shall follow guidelines set forth by the Public Works Department. The roads in Crockett at the construction site are narrow and not conducive to safely keeping one lane of two-way traffic open during construction. Therefore, it is recommended to close the road to through traffic during construction hours to increase traffic safety and to improve construction efficiency to help shorten the duration of work in the right of way.
|