RECOMMENDATION(S):
ADOPT Resolution No. 2020/35 accepting as complete the contracted work performed by Kerex Engineering, Inc., for the San Pablo Dam Road Sidewalk Gap Improvements Project, as recommended by the Public Works Director, El Sobrante area. County Project No. 0662-6R4020, Federal Project No. HSIPL-5928(133) (District I)
FISCAL IMPACT:
The Project was funded by 68% Highway Safety Improvement Program Funds, 11% Transportation Development Act Funds, and 21% Local Road Funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of November 1, 2019.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
|