RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract amendment with AECOM Technical Services, Inc. (AECOM), effective March 2, 2019, to extend the term from March 1, 2019 to December 31, 2019, for on-call civil engineering services, with no increase to the original payment limit of $250,000, Countywide. (County Project No. 0662-6R6113)(All Districts)
FISCAL IMPACT:
Work performed under this amendment is funded by 100% Local Road Funds.
CONSEQUENCE OF NEGATIVE ACTION:
If the contract amendment is not approved, the Pacheco Avenue Alignment Study, Blum Road to Morello Avenue will experience delays and added costs as the County solicits for new professional services which will duplicate previous work.
|