RECOMMENDATION(S):
APPROVE and AUTHORIZE the Conservation and Development Director, or designee, to execute a tolling agreement with GTE MobileNet of California (dba Verizon Wireless), to extend the time to act on a permit application for a wireless telecommunications facility proposed in the Alamo area of unincorporated Contra Costa County to March 31, 2016 and beyond, if needed.
FISCAL IMPACT:
None. The applicant has paid the necessary application processing fees and is obligated to pay supplemental fees to recover any and all additional staff time and materials associated with application processing.
BACKGROUND:
Verizon Wireless has filed a land use permit application to construct a stealth wireless telecommunications facility within the Alamo area (County File Number LP15-2018). The application was filed with the County on May 21, 2015. The County issued a notice of incomplete application on June 9, 2015. Verizon Wireless provided all the required information on August 5, 2015. The County issued a notice of complete application on August 6, 2015.
|