RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract with Timothy J. Clay (dba Diablo Boiler) in an amount not to exceed $1,500,000 to provide boiler service repair and maintenance, for the period February 1, 2016 through January 31 2019, Countywide.
FISCAL IMPACT:
This cost is to be funded through Facilities Services maintenance budget. (100% General Fund)
BACKGROUND:
Public Works Facilities Services is responsible for maintenance of all hot water, boiler furnace and heat pump systems at County facilities. Scheduling this maintenance is done by Facilities Services, but the actual maintenance is performed by outside vendors. As bid on Bidsync # 1510-158, Diablo Boiler has been awarded this work. We are requesting this contract be approved for a period covering the next three years.
|