RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute Contract Amendment No. 1 to the Consulting Services Agreement (CSA) with Hanna Engineering, Inc., dba The Hanna Group (Hanna), effective January 12, 2015, to increase the payment limit by $45,000 to a new payment limit of $379,000, for construction management services for the San Pablo Avenue at Rodeo Creek Bridge Replacement Project, Project No. 0662-6R4005/Federal Project No. BRLS-5928(067)
FISCAL IMPACT:
This project, including the CSA, is funded by 88.53% Federal Highway Bridge Program (HBP) Funds and 11.47% Local Road Funds.
BACKGROUND:
The Public Works Director, or designee, executed a CSA, dated July 8, 2014, with Hanna for construction management services for the San Pablo Avenue at Rodeo Creek Bridge Replacement Project.
Proposed Contract Amendment No. 1 will amend the payment limit of the CSA so that the Consultant can be compensated for providing additional construction management services.
|