RECOMMENDATION(S):
APPROVE the Upper Sand Creek Basin Project contingency fund increase of $1,000,000 for a new contingency fund total of $1,911,688.50, and a new payment limit of $11,028,573.50, effective February 11, 2014, and
APPROVE and AUTHORIZE the Chief Engineer, or designee, to execute Contract Change Order Nos. 4 and 5 with Goodfellow Top Grade Construction, LLC, effective February 11, 2014, in an amount not to exceed $214,273.68 for Contract Change Order No. 4 and $164,704.50 for Contract Change Order No. 5.
|