RECOMMENDATION(S):
APPROVE the Upper Sand Creek Basin Wetland Restoration Project contingency fund increase of $22,000 for a new contingency fund total of $35,804.19, and a new payment limit of $173,846.09, effective February 4, 2014, as recommended by the Chief Engineer, and
APPROVE and AUTHORIZE the Chief Engineer, or designee, to execute Contract Change Order No. 1 with SMP Services, Inc., effective February 4, 2014, in an amount not to exceed $20,434.00. Project No. 7562-6D8518-13
|