RECOMMENDATION(S):
APPROVE the Arlington Avenue Curb Ramp project contingency fund increase of $6,000, for a new contingency fund total of $21,200, and new payment limit of $173,202, effective February 12, 2013; and
ADOPT Resolution No. 2013/83 accepting as complete the contracted work performed by Sposeto Engineering, Inc. for the Arlington Avenue Curb Ramp project, as recommended by the Public Works Director,Kensington area. (Project No. 0662-6R4207)
FISCAL IMPACT:
Project was funded by 100% Local Road funds.
|