County
Subject: Accept Resolution of Acceptance and Notice of Completion for the Parking Lot "C" Expansion at the Contra Costa Regional Medical Center

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   02/08/2011
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Gayle B. Uilkema, District II Supervisor
Mary N. Piepho, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Mike Lango (925) 313-7100
cc: GSD Administration     GSD Accounting     GSD CPM Division Manager     GSD CPM Project Manager     GSD CPM Clerical     Auditor's Office     County Counsel's Office     County Administrator's Office     County Administrator's Office    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     February  8, 2011
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2011/44 accepting as complete the contracted work performed by Bruce Carone Grading & Paving Company, 2500 Alhambra Avenue, Martinez, for the Health Services Department, as recommended by the General Services Director.

FISCAL IMPACT:

There is no fiscal impact resulting from the adoption of the Resolution of Acceptance and Notice of Completion.

BACKGROUND:

On July 14, 2010, the County entered into a contract with Bruce Carone Grading & Paving Company for the Parking Lot "C" Expansion at the Contra Costa Regional Medical Center. The project has been completed in accordance with the approved plans and specifications and it is recommended that the project be accepted. The amount of $11,599 is being withheld pending completion of additional irrigation work and project closeout.

CONSEQUENCE OF NEGATIVE ACTION:

Accepting the project as complete is standard procedure and allows for proper close-out of the project.