C.5
To: Board of Supervisors
From: Julia R. Bueren, Public Works Director/Chief Engineer
Date: February  3, 2009
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Accepting Completion of Warranty Period and Release of Cash Deposit for Faithful Performance for the Subdivision Agreement (Right-of-Way Landscaping),

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   02/03/2009
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Gayle B. Uilkema, District II Supervisor
Mary N. Piepho, District III Supervisor
Susan A. Bonilla, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Jocelyn LaRocque (925) 313-2315
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     February  3, 2009
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2009/36 accepting completion of warranty period and release of cash deposit for faithful performance for the Subdivision Agreement (Right-of-Way Landscaping), for Road Acceptance 04-01170 (cross-reference Subdivision 03-08509), for project being developed by Lennar Homes of California, Inc., as recommended by the Public Works Director, San Ramon (Dougherty Valley) area. (District III)

FISCAL IMPACT:

None.

BACKGROUND:

The landscape improvements have met the guarantee performance standards for the warranty period following completion and acceptance of the landscape improvements.

CONSEQUENCE OF NEGATIVE ACTION:

The developer will not receive a refund of their cash deposit, the Subdivision Agreement (Right-of-Way Landscaping and performance surety bond will not be exonerated, and the billing account will not be liquidated and closed.