RECOMMENDATION(S):
APPROVE and AUTHORIZE the Director of Airports, or designee, to execute an extension to the consultant services agreement with Barnard Dunkelberg & Company, effective October 2, 2008, through June 30, 2009, in the original contract amount of $105,264 for the Buchanan Field Airport Runway Safety Area Study, Airport Improvement Program (AIP) Project No. 3-06-0050-15. Pacheco Area. (District IV)
FISCAL IMPACT:
There is no impact on the General Fund. The total contract cost for the Runway Safety Area Study is $105,264, of which $2,764 is from the Airport Enterprise Fund, $2,500 from CALTRANS, and $100,000 is funded from FAA Airport Improvement Program. The contract extension is only for additional time and no additional funding is required to complete the project.
BACKGROUND:
On June 7, 2005, the Board of Supervisors authorized the submission and acceptance of grant applications to the Federal Aviation Administration and CALTRANS to perform the Buchanan Field Airport Runway Safety Area Study.
|