To: Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: December  13, 2022
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: APPROVE the Contingency Fund Increase for the Fred Jackson Way First Mile/Last Mile Connection Project, North Richmond area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   12/13/2022
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
ABSENT:
John Gioia, District I Supervisor
Contact: Adelina Huerta, 925-313-2305
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     December  13, 2022
Monica Nino, County Administrator
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE the Fred Jackson Way First Mile/Last Mile Connection Project contingency fund increase of $921,000.00 for a new contingency fund total of $1,759,756, and a new payment limit of $4,147,313.25, effective December 13, 2022, as recommended by the Public Works Director.

FISCAL IMPACT:

The Project is being funded by 5% State Coastal Conservancy (SCC) Prop 1, 74% Active Transportation Program, 5% North Richmond Area of Benefit, 16% Transportation for Livable Communities.

BACKGROUND:

The contingency fund increase is necessary to compensate the contractor for unforeseen extra work required to complete the project. Due to unexpected utilities and a change in conditions during road reconstruction, a new design for the roadway was required. This created a change to the contract which was reflected in contract change orders. The new design reduced and eliminated approximately $583,000 in bid items from the original contract and the new design was paid for under Contract Change order no. 5, which was approved at the July 12, 2022 Board of Supervisors meeting. However, additional grinding and disposal of unsuitable materials was necessary and resulted in additional change orders to be paid from the contingency fund.


CONSEQUENCE OF NEGATIVE ACTION:

The lack of approval would prevent successful completion of this contract and prevent payment for the additional work performed by the contractor.