RECOMMENDATION(S):
APPROVE and AUTHORIZE the Chief Engineer, Contra Costa County Flood Control and Water Conservation District (FC District), or designee, to execute a contract amendment with Environmental Science Associates (Contractor), effective November 17, 2020, to increase the payment limit by $300,000 to a new payment limit of $1,950,000, to continue providing services to the FC District in connection with the Lower Walnut Creek (LWC) Restoration Project, and to extend the termination date from January 31, 2021 to January 31, 2022, Martinez area.
FISCAL IMPACT:
This phase of the project is funded by a combination of Flood Control Zone 3B (Walnut Creek watershed) funds and grant funds from the Environmental Protection Agency (EPA) and the California Department of Fish and Wildlife (CDFW). (51% Flood Control District Zone 3B Funds, 32.5% CDFW Proposition 1 Grant Funds, and 16.5% EPA San Francisco Bay Water Quality Improvement Funds)
|